Services installed:

Process Pipe Work, Ventilation, Chilled & Domestic Water

Project Scope:

Baby Food Manufacturing

All works were carried out during 24 hour shutdown periods.

Steam Service Works Included:

  • Flow Meter Installation, Steam P.R.V.’s,
  • Heat Exchanger Installation,
  • Steam Strainers, Steam Air Vents Installations,
  • Steam Traps and Steam Valves.

Chilled Water Services Included:

  • Balancing Valve Data, Gate Valve Data,
  • Ball Valve Data, Strainer Data
  • Butterfly Valve Data and Flow Switch Detail